Example
A paint shop as the bottleneck
A furniture manufacturer is planning a second painting line for several million euros, because the existing one is fully utilised and delivery times are rising. The analysis shows that the line stands still during breaks and shift changes, and almost one part in ten is painted even though it already had a defect and is later rejected.
The company introduces overlapping breaks, moves quality inspection in front of the paint shop and schedules the sequence by colour to save cleaning time. Throughput rises by around a fifth, and the investment is postponed. The example is invented.