Example
What it looks like in a project
A machinery maker invests in faster milling machines, but on-time delivery stays poor. The bottleneck is final assembly with three skilled workers. A fourth skilled worker achieves more than the machines.
TOC
Every system is limited by one bottleneck. Improve that, not everything else.
The theory of constraints says that a system’s performance is determined by its weakest link. Any improvement outside the bottleneck has no effect. The procedure: find the bottleneck, exploit it fully, subordinate everything else to it, elevate it, then look for the next bottleneck.
OriginEliyahu M. Goldratt, “The Goal”, 1984.
Example
A machinery maker invests in faster milling machines, but on-time delivery stays poor. The bottleneck is final assembly with three skilled workers. A fourth skilled worker achieves more than the machines.
Look for the bottleneck where work piles up.
Make sure the bottleneck never waits: a buffer in front of it, staggered breaks, quality checks before it.
Measure the throughput of the whole system, not the utilisation of individual stations.
Aiming for high utilisation everywhere. Full utilisation upstream of the bottleneck only creates inventory.
A management approach by Eliyahu Goldratt according to which a system’s performance is determined by one bottleneck, on which all improvement should focus.
APA (7th edition)
Benchreads. (2026). Theory of constraints: meaning, example and application. Retrieved 25 November 2026, from https://benchreads.com/en/glossary/theory-of-constraints/
Benchreads is a secondary source. For academic work, also cite the original sources named in the text. You are welcome to link to this page in course materials.
Last updated: 25 November 2026. Carefully researched, but without guarantee. Not legal, tax or investment advice. Disclaimer