Example
An acquisition in wholesale
A plumbing and heating wholesaler acquires a regional competitor. The approach is absorption: shared warehouses, one ERP, one brand within 18 months. The IMO plans 14 functional teams. Two weeks before closing, the Day One check shows that the supplier master data cannot be transferred. The team decides to run the systems in parallel for six months.
The acquired company’s sales management is confirmed in the first week, with retention bonuses for twelve months. Customer churn in the first year is 3 percent instead of the feared 10 percent. The purchasing synergies arrive faster than planned, the logistics synergies a year later because of the delayed ERP switch. The example is invented.