Example
A construction company aggregates its project risks
A construction company assesses its risks with a matrix and reports two red and eleven yellow fields to the supervisory board. Nobody can say whether the company would survive a bad year. The team quantifies the 25 largest risks in ranges, takes into account that material prices and interest rates can rise together, and calculates 10,000 simulated years.
Result: there is a probability of about 25 percent that the earnings target will be missed. In a year that occurs only once in twenty years, there is a liquidity shortfall of 60 million euros, against a buffer of 45 million. The company negotiates an additional credit line and introduces price escalation clauses for large projects. The example is invented and the figures are illustrative.